Hi ,
First of all ,SAP has replaced revision 84 with 85(I am not sure about the reason)
1. Master guide says stop processes, what process should i stop?
Application servers,but not the DB (but while you upgrade DB onHA ,you need to stop the DB as well)
2.This is a BW on HANA system, anything specific do i have to take care before updating?
- Make sure you have a successful consistent Data backup
- on ABAP run the program BTCTRNS1 to deschedule the jobs
- Stop SLT replication
- Stop Cron jobs for Backup
- Confirmation from BW Consultant that the Queues are clear
- Screen shots of Overview Tab,Alerts tab
3.Any poststeps i have to take care of, after update?
- HANA Client Upgrade on the application instance(Solution manager, ECC,BI,SLT)
- Start SLT
- Start Cron Jobs
- Data Backup
- check for Error and warning on application and DB
- execute Program BTCTRNS2
- Functional checks
4.Should i ask all users not to use system till update is over?
- users has to be logged off on DB's however you have options to do the changes with zero downtime, for more information check the below SAP notes
I am updating server, hostagent and client? how about studio, it has to be updated from respective client machines , correct?
yes,Must do it
2052914 - ODBC driver issue after upgrade to Revision >= 82
All the best with your upgrade
Cheers,
George